"An off-set signalized 104-foot-wide crosswalk that is activated by pressing a button on the signal pole." That's how San Ramon's 2018 environmental study described the spot where the Iron Horse Trail meets Crow Canyon Road. The road there is eight lanes and 103 feet wide, with a 17-foot landscaped median. The trail crossing also doesn't line up with any cross street, so the signal is there only for trail users.
On September 21, the City Council voted 5–0 to start replacing that crossing with a bridge. The vote does less than the headlines suggest, and San Ramon's last trail bridge shows what still has to happen. On that schedule, the button at Crow Canyon will be part of trail use for years.
What the $2.06 million actually pays for
The Council approved an agreement with the engineering firm Mark Thomas for up to $2,059,133. Councilmember Sridhar Verose made the motion and Councilmember Richard Adler seconded it. The contract covers design and engineering only. In its coverage of the vote, the Bay Area Telegraph wrote that construction "will require additional funding."
The design money has been waiting for a while. San Ramon received a $2 million federal Community Project Funding allocation for design in June 2022. The General Fund adds a $233,232 match, for a design budget of $2,233,232. After the Mark Thomas contract, $174,099 of that is left.
The contract is wide in scope. The city's request for proposals asked for final engineering, construction documents, cost estimates, utility and right-of-way work, permits, and support during construction. The city's written answers to bidders said design was fully covered by federal and city-match funds and that "additional funding is being sought for right-of-way and construction." Those answers didn't name a specific construction grant.
That means the design is funded and the bridge isn't.
Bollinger Canyon is the schedule to measure against
The Iron Horse Trail Overcrossing at Bollinger Canyon Road opened on July 19, 2025. It came out of the same planning work as Crow Canyon. A 2009 corridor concept plan studied both crossings, and a community outreach process that ended in 2015 picked concept bridge types for both. Since they started together, Bollinger's timeline is the best local guide to what Crow Canyon faces.
| Milestone | Bollinger Canyon | Crow Canyon |
|---|---|---|
| Concept bridge type chosen | 2015 | 2015, tied arch; changed to butterfly arch December 12, 2023 |
| Final design | Approved April 23, 2019 | Design contract approved September 21, 2026 |
| Construction start | Groundbreaking May 18, 2023; road impacts from week of July 31, 2023 | City lists 2028–2030, "funding dependent" |
| Opening | July 19, 2025 | Not scheduled |
| Cost | $20.8M estimate in 2019; about $29M final | $20.1M–$22.1M in 2023 dollars; roughly $24M per a September 2026 meeting recap |
At Bollinger, final design approval came more than six years before opening. Construction alone took about two years. Crow Canyon's design contract is only a few weeks old.
The city's own schedule needs some caution too. The Crow Canyon project page still says design "is expected to begin in 2025" and lists design for 2025 through 2027. The design agreement didn't reach the Council agenda until September 21, 2026. The Telegraph called the 2028–2030 construction window a planning estimate, and that's the right way to read it.
Bollinger's price went up before it was built
The funding history matters more than the dates because it shows how a bridge actually gets built in San Ramon. At a March 26, 2019 workshop, the Council expressed unanimous support for a cable-stayed design with a center pylon in Bollinger Canyon Road. The estimate was $20.8 million, which was $6.5 million more than the funding the city had identified. The Council told staff to look for more grants. If that fell short, staff were to pursue financing that could be repaid over time with Measure J Return to Source funds.
That plan is close to what happened. The city's 2023 project FAQ put the full cost at about $29.1 million. It listed $10.5 million in grants, $13.2 million in Measure J advance funds, $2.9 million in long-term debt, and $2.5 million in other city funds. The city later said more than 82% of the money came from outside sources. Those included the Bay Area Air Quality Management District, MTC's Transportation for Livable Communities and One Bay Area programs, the Tri-Valley Transportation Commission, and the Contra Costa Transportation Authority's Measure J.
The bridge turned out well. It's 340 feet long and cable-stayed, with 900 feet of approach walls, more than 7,000 native and drought-tolerant plants, and 80 trees. In February it won the 2026 Outstanding Local Streets and Roads Project Award from CSAC, Cal Cities, and CEAC. It also won two American Public Works Association honors, including the 2026 Northern California APWA Project of the Year. Public Works Director Brian Bornstein called it "an instant landmark in the heart of San Ramon" and said it was finished "on time and within budget." The city's May 2023 FAQ had targeted completion "by the end of 2024," and the opening came about seven months after that.
Crow Canyon is starting from the same position Bollinger was in back in 2019. It has a chosen design and a cost estimate, and it doesn't have construction money. The November 2023 concept update estimated the butterfly arch at $15,185,000 for construction and $20,085,000 to $22,085,000 for the whole project, in 2023 dollars. A secondary recap of the September meeting credits staff with a rough total of about $24 million. The original staff report wasn't available to check that figure, so treat it as a ballpark.
The design work has to fit a tight spot
Part of what Mark Thomas will spend the next few years on is fitting the bridge into the corridor. The Iron Horse Trail corridor is at its narrowest where it crosses Crow Canyon Road, with a 65-foot easement to the north and a 50-foot easement to the south. Inside that space are a 34-foot easement Contra Costa County set aside for a possible future light rail line, a Kinder-Morgan petroleum line along the east edge, storm drain easements beneath and beside the trail, and PG&E overhead power lines running alongside it. The 2023 estimate set aside up to $2 million for right-of-way and for avoiding or moving utilities.
The land around the crossing is mostly institutional. PG&E offices and a substation sit to the northeast, a school district maintenance facility to the northwest, Iron Horse Middle School and a church to the southeast, and the San Ramon Valley Conference Center parking lot to the west.
The bridge type has already changed once. The Council selected a tied arch on July 14, 2015. When the city reopened outreach in 2023, the community chose a butterfly arch, and the Council accepted it on December 12, 2023, under Resolution 2023-134. The concept report says the exact alignment and approach details will be settled in final design. When the bridge is built, the signal and the street-level crosswalk will be removed.
What Crow Canyon looks like this fall
The crossing still works the way the 2018 study described it, and this fall Crow Canyon Road is also a work zone. The city's annual resurfacing program runs from September into December, with Goodfellow Bros. handling asphalt, curb ramps, and concrete. The city has warned of lane closures, no-parking notices, and minor delays. The September 23 proposed schedule lists these dates for Crow Canyon Road between Bollinger Canyon Road and Alcosta Boulevard:
- Concrete work: September 28 through October 30, 2026
- Paving: November 9 through November 20, 2026
A busy morning is coming right next to the crossing. The 43rd annual Run for Education starts at Iron Horse Middle School, 12601 Alcosta Boulevard, on Sunday, October 11, from 8 a.m. to noon. Proceeds go to local public schools.
When the bridge does go into construction, Bollinger's experience gives a sense of what to expect. For roughly two years, the north-side trail next to Bollinger Canyon Road was closed for a long stretch, and then the south side closed, with detours for bikes and pedestrians. Drivers had one lane closed on each side near City Hall and a 30-mph work zone. Nothing for Crow Canyon has been scheduled. The September vote paid for the drawings, and until construction funding is found, trail users will keep using the button.
At Julie Whitmer, we follow projects like the Crow Canyon overcrossing because they change the San Ramon that homeowners live in, often more slowly than the headlines suggest. If you'd like to talk through how a city project near your street fits your plans, schedule a complimentary home strategy call.