Contractors have until 2 p.m. this Wednesday, October 14, to submit bids on the Livorna Park Improvements Project. The County estimates the base bid at $2,520,000. The April environmental notice expected construction to begin in July 2026. July has come and gone without a contract. The County planroom still lists the job as "Accepting Bids" and names no builder.
The delay is the smaller story. The bigger one is that this package answers a question Alamo has argued over for close to a decade: is Livorna Park a quiet park for the streets around it, or a gathering place for the whole town? Look at the plan item by item and the County's answer is clear. Nearly everything in it, from the full-size court to the water play, assumes people will come from all over Alamo.
Where the project stands this week
| Date | Milestone |
|---|---|
| March 2022 | Public Works raises the need to renovate with Supervisor Candace Andersen's office |
| Early 2023 | First community survey opens |
| May 7 and 15, 2024 | Public meetings on the draft plan |
| December 3, 2024 | Revised master plan issued for review |
| April 27, 2026 | Board of Supervisors approves the project 5-0 |
| July 2026 | Projected construction start, which did not happen |
| October 14, 2026 | Bids due |
The Board approved the renovation as a consent item. It's paid for entirely with County Service Area R-7 funds. That funding source matters to the argument. The County's Livorna Park FAQ says all Alamo residents and businesses support the R-7 fund, and the money can be spent only inside Alamo's R-7 boundary.
Once a contract is signed, the environmental notice estimates about 320 working days of construction. That's roughly 64 five-day work weeks. The County hasn't published a reopening date, so any finish date you hear now is a guess.
A 2017 report said this park had outgrown its purpose
The renovation is the latest chapter of an argument that came to a head in 2017. That year, Contra Costa County Grand Jury Report 1711, "Alamo Parks Planning and Development," looked closely at Livorna.
The Jury read the park against the County General Plan's definition of a neighborhood park. Under that definition, a park meant to serve people within about half a mile should be limited to trees, grass, shrubs, benches, tables and walkways. The report described Livorna this way:
"Livorna Park sits within a quiet residential area surrounded by single family homes. It was built to accommodate nearby residents and provides parking for 17 vehicles."
The Jury listed what had been added over the years without the park getting any bigger: a playground, a volleyball court, a gazebo, and a bocce court facility in 2016. It noted that summer concerts could draw more than 500 people, some from neighboring cities. Its suggestion was to move large events to Hap Magee Park, which it described as 16.3 acres with parking for 89 vehicles. It also found that the R-7 fund had no long-term spending plan, even though the fund balance was about $3.51 million in fiscal year 2015–16.
The Board of Supervisors approved its response on August 1, 2017. The Board disagreed with most of the findings and said Livorna had been created as a community park serving all of Alamo. It agreed that park hours had been changed without consulting neighbors, and that Hap Magee is larger and has more parking. It declined to move events to Hap Magee. Its reasons were that the Town of Danville, which runs that park jointly with the County, could veto events there, and Hap Magee's master plan discourages nighttime use.
The County's current FAQ states its position in a single line:
"The County no longer categorizes parks as neighborhood parks. Livorna Park is a community park, funded by all of Alamo residents."
What the plan builds, and which side of the argument each piece serves
The project began with a practical problem. The County's annual playground inspections found that Livorna's play structure had reached the end of its life. The FAQ also describes the park as nearly 30 years old and says the bathroom needs major repairs. From there, the plan grew into something larger than a playground swap.
| Element | What the plan calls for | How it connects to the debate |
|---|---|---|
| Playground | Replaces the 8,400-square-foot play area with inclusive equipment, swings and a fenced area for ages 2 to 5 | The original trigger for the project |
| Sports court | Expands to full size for basketball and other sports; the preliminary plan proposed one more pickleball court | The Alamo MAC and many residents asked for it, citing more families wanting a larger court |
| Water play | Adds a misting and water-wall feature | Runs only in warm weather and recirculates its water |
| Picnic and shade | Seven picnic tables and more shaded seating | Built for longer visits |
| Bocce | Repairs the existing court | The 2016 addition the Grand Jury questioned |
| Landscaping | About 58 trees and 12,500 square feet of shrubs planted, about 15 trees and 7,500 square feet removed | Tree removal drew objections in 2024 |
Sources for the table: the environmental notice for the playground footprint, court, water play and planting counts; the County's revised master plan dated December 3, 2024, for the play areas, picnic tables and shade; and the FAQ for the court request and how the water feature works.
Parking shows how far apart the two readings of the park are. The FAQ says the lot has 13 spaces and is often full, which pushes people onto nearby streets and has children crossing roads. The 2017 report counted 17. In the 2017 report, limited parking was evidence that the park was built for neighbors. In the County's version, the same limited parking is a safety problem to solve with more spaces.
What came up at the 2024 meetings
The County's notes from the May 7 and May 15, 2024 sessions record a split that's easy to recognize. Some attendees said they never received project notices. Others objected to pickleball noise, the full-size court, more parking, tree removal, and a relocated pavilion near Easy Street, and some raised concerns about added crowds and traffic. Supporters asked for the splash pad, a bigger basketball court, slides and more seating. One participant said the park serves children and families.
The tally in those notes was small. The basketball court drew eight "dislike" responses, parking drew five, and the splash pad drew three. Attendees also questioned how far the survey had reached. They noted about 250 responses in a community of roughly 14,000 and asked for direct mail to homes near the park. According to the FAQ, the second survey went out by postcard to every Alamo residence. The FAQ adds that the survey was "not an election." It was one input for the Alamo MAC and Supervisor Andersen.
The notes also say Stantec was redesigning the pavilion, and attendees asked that it be moved farther from Easy Street with its sound aimed away from homes. The records reviewed don't confirm where the pavilion ended up. Some neighbors suggested keeping pickleball low-key, with a single court or children's use. The County's FAQ describes the preliminary plan as adding one more pickleball court to the expanded multi-sport court.
The approved project keeps every amenity the Grand Jury questioned and adds a full-size court, water play and more seating.
The park this fall, and the places to know once fences go up
For now, Livorna is the park Alamo has used for years. The 2026 Alamo Summer Concert Series ran there on four Friday evenings in July, July 10, 17, 24 and 31, from 6:30 to 8:30 p.m. The bands were The Sun Kings, Fourjour, Highway Vagabonds and Fog City Swampers. No source has said yet how construction will affect next summer's concerts or Movies in the Park.
If construction does close the playground and court, these are the nearby options:
- Hap Magee Ranch Park has separate play areas for younger and older children, picnic areas, a dog park and walking trails. Its water play runs April 1 through September 30, so it's already off for the winter.
- The Alamo School shared-use site is a 2.5-acre recreation area with baseball and soccer fields, a batting cage, paths, a picnic and barbecue area, and two multi-use courts. The County says both the public and the school district can use it.
- The Iron Horse Trail has staging areas at Danville Boulevard and Stone Valley Road and connects Alamo to Danville. Riders heading north should know that the Robert I. Schroder pedestrian bridge over Treat Boulevard in Walnut Creek is closed October 5 through December 31, 2026.
The next public step is the bid opening on October 14. The award that follows will name the contractor and the actual contract price. It may also produce the first real construction start date since the July projection passed.
A long construction period at a well-used park affects the homes around it, from street parking to weekend noise. If you live near Livorna Road or Miranda Avenue and want to talk through what that could mean for your plans over the next year, Julie Whitmer and her team are glad to help. Schedule a complimentary home strategy call.